SOMERS SCHOOL BUILDING
CONSTRUCTION COMMITTEE
May 22, 2003
Members Present: J.Butler,
H.Broer, J.Formeister (7:55) , J. MacFeat, J.O'Brien, T.Cowles, P. Roland (8:10)
Ex-Officio: B.Boutwell
(8:00) , T.Jefferson (9:00), K. Klein
Others: M. Beaulieu
The meeting was called to
order at 7:31 by T. Cowles.
Minutes of the 4/24/03 meeting
were unanimously approved as presented (Butler, Broer).
There were no citizens’
comments.
Michelle Beaulieu and Macchi
Engineers began the presentation with the civil works drawings.
SHS was the first school to be
reviewed:
Macchi engineers stated that
it is anticipated the regrading of the areas as well as the excavation would
not require additional fill material to be brought in for the SHS project.
J. MacFeat brought up a
concern with the curbing as it pertains to the snow removal. A curb in
the area of the truck turn around would be an obstacle. Macchi engineers
felt that without a curb the East Side of the turn around will be susceptible
to erosion and become a maintenance item also Macchi stated that a guardrail
maybe required. Macchi agreed to investigate the use of trap rock on the
side hill to the east of the turnaround as a way to prevent the erosion and
they will present an option at a later date.
T. Cowles questioned the need
for concrete versus bituminous walkways to the two new exits as well as the
connecting walkway to the front walk. The cost differential would be
approximately $12.00 sq. ft for concrete versus $2.50 sq. ft. for
"bituminous". No vote was taken therefore the change will be
discussed at the next meeting.
M. Beaulieu discussed the
science teachers’ requirement for work benches in the new labs and the decision
on the functionality of the hardware selections. "Smart boards"
were also discussed and a motion to approve Smart boards for each of the
science room was approved by the committee. ( Roland, Butler )
The Media Center renovations
were discussed and the committee voted (Cowles, Roland) to keep the doors
according to the plans. The architect will pursue with the SHS staff the
relocation of the IT director’s office.
SES was then reviewed:
The civil drawings were
reviewed and it was questioned why the driveway connector from the SHS
teachers' parking lot to the SES parking lot was not included with the SHS
project. It appears that the work would be accomplished at a lower cost
if it was to be included in the SHS. The committee will explore this option as
we proceed with the SHS project.
After a lengthy discussion the
Building Committee voted (Cowles, Roland) and instructed the architect that the
cafeteria expansion will include the extra space as well as the additional
mobile serving line. Further the architect was instructed that the
warming oven could be included with the expansion with the funds coming from
FF&E.
The architect was further
instructed by a committee vote to follow the Alternate Route for firewater
source to the additional classrooms with anticipated cost savings of $35,000
based on the consulting engineer's estimate. (Cowles, Formeister)
MBA was next to be reviewed:
The civil drawings were not
ready and therefore they were not reviewed.
The committee did discuss at
length the need to have construction laydown area and marshalling yard for the
contractor's materials and equipment. The committee voted (Roland,
Butler) and then instructed the architect to be very clear with a special note
to all bidders that a material and equipment management and staging plan have
to be included in the General Contractors bid document. And it was
stipulated that the plan include removal of the unnecessary materials and
equipment from the local vicinity of each of the building projects each night.
The committee then heard from
M. Beaulieu on the phasing plan for the middle school, paying specific
attention to the floor plan for the Central Office. It was decided to
eliminate the coat closets from each office in favor of a central coat area.
In addition a new floor plan showing a shifting of the Curriculum
resource person/people to an area closer to the Curriculum Director was
requested. MoserPilonNelson will rework the floor plan to accommodate the
curriculum department.
Invoice payments:
The committee voted and
approved (Roland, Cowles) the following invoices:
Vendor
Amount $
Date Invoice #
PO reference
Moser Pilon Nelson
14,789.00 5/2/03
013051 PO # 20783—SES
Moser Pilon Nelson
14,445.00 5/2/03
013050 PO # 20782—MBA
Moser Pilon Nelson
17,148.00 5/2/03
013052 PO # 20719—SHS
Moser Pilon Nelson
29.88 5/2/03
013052
reimbursable—SHS
$46,411.88
Moser Pilon Nelson
8,873.40 5/22/03
013051 PO # 20783—SES
Moser Pilon Nelson
19,260.00 5/22/03
013051 PO # 20783—SES
Moser Pilon Nelson
8,574.00 5/22/03
013051 PO # 20783—SES
Moser Pilon Nelson
3.98
5/22/03 013051 PO #
20783—SES
$36,711.38
The Committee voted and
approved ( Roland, Butler) the remaining portion of the surveyor's invoice upon
receipt of the outstanding drawings.
John Butler,
Acting Secretary in Madam
Secretary Formeister's absence
Joan Formeister, Secretary