SOMERS SCHOOL BUILDING
CONSTRUCTION COMMITTEE
November 20,
2003
Members
Present: H.Broer, T.Cowles,
J.Formeister, J.Butler, P.Roland, D.Pinney
Ex-Officio: B.Boutwell, T.Jefferson (7:55), K.Klein
(9:12)
Others: D.Moser
The meeting
was called to order at 7:34pm by Chairman Roland.
Minutes of
the 8/28/03 meeting were approved unanimously as presented (Broer,
Butler). Minutes of the 9/25/03 were
approved unanimously with a correction in paragraph 2, line 6, “meet”, and the
last line in paragraph 2 should read “The Building Committee determined this
work will not be included in this project” (Butler, Broer). Minutes of the 10/30/03 meeting were
approved unanimously with a correction in paragraph 3, line 2, “of” (Cowles,
Butler).
Bid
document---P.Roland and D.Moser have spoken with Att’y Brad Wolf, who said the
document was very good, but he has not forwarded it yet. Since the committee cannot wait till the
December meeting to review it, his comments will be e-mailed to members. He will be invited to speak with us before
we open bids. MPN will first analyze
bids when they come in.
SHS---SFU
expects to be finished with plans by the end of November. A stormwater
management letter from the DEP is not in yet but should be this week. A copy of a letter was read from T.Jefferson
to the Somers Building Official with chemical calculations for the Fume
Hoods. The committee decided the
marshalling yard should be changed from SES grounds to the tennis courts at
MBA. We will advertise to hire a Clerk
of the Works for a start date around 2/1/04.
If drawings are back from the state 12/1, the bid document will go out
the second week of December and bids will be in by mid-January. A legal notice will be done by the Town
Clerk when we advertise for bids; D.Pinney to check into this.
Budget,
estimates, timeline---we’re within a month or two of original plans. SES will be following SHS closely. A report from T.Jefferson was reviewed which
incorporated new enrollment projections, cost estimates, contingencies, and
reimbursable figures for all projects.
Budget and estimates remain essentially unchanged. MBA will be ready to go earlier than the
original timeline; BOF will need to consider when they want this project
started.
SES---meeting
11/18 with SFU went well. Plan
Completion Test Sheet was distributed, with list of items to be addressed by
MPN, who will meet again with SFU the first week of December. The State is taking 30-60 days for review of
plans. There was brief discussion about
the cafeteria expansion. A motion was
made (Pinney), seconded (Butler), and unanimously approved to have MPN look at
the cafeteria expansion as an alternate in the bid process.
MBA---plans
are developing further, minor changes were reviewed. Michele Beaulieu will meet with the staff before Christmas.
Relocation
C.O.---$40,000 was budgeted. In case
Kibbe Fuller is not available as an option, other spaces will be looked at,
such as the old firehouse, rental space, space in SES or SHS after those
additions are complete and before students are moved in. A committee including members of C.O. staff
and H.Broer will investigate options.
It was the
consensus of the committee that we should meet December 18. A schedule of meetings for 2004 will be
presented at that time, to continue with the fourth Thursday of each month and
2 meetings in February.
A letter
was received from D.Moser concerning asbestos and suggestion that we hire a
firm to do an inspection. A motion was
made (Cowles), seconded (Pinney), and unanimously approved that we obtain three
bids for an asbestos study.
Motions
were unanimously passed to pay the following bills:
MPN Inv.#13334, SES
$3074.93 (Cowles, Broer)
MPN Inv.#13333, MBA
$25,680.00 (Butler, Cowles)
MPN Inv.#13332, C.O.
$3110.40 (Cowles, Butler)
Meeting
adjourned at 9:41pm.
Respectfully
submitted,
Joan
Formeister, Secretary