SOMERS SCHOOL BUILDING CONSTRUCTION COMMITTEE

                                                     December 18, 2003

 

Members Present:  J.MacFeat, H.Broer, T.Cowles, P.Roland, J.Formeister,

                               J.O’Brien (7:38), D.Pinney (7:38)

Ex-Officio:  B.Boutwell, T.Jefferson

Others:  D.Moser

 

The meeting was called to order at 7:30pm by Chairman Roland.

 

SHS---D.Moser presented copies of SHS Project Schedule.  A meeting will be held 12/19/03 with SFU.  It is expected the State will issue an authorization to bid 1/14/04 with construction starting 3/16/04.  The SFU is waiting for the State Fire Marshall’s review.  Brief discussion about hiring Clerk of the Works.  A motion was made (Cowles), seconded (Broer), and unanimously approved for P.Roland to advertise for Clerk of the Works.  Three prices were presented for printing of bid sets.  A motion was made (Cowles), seconded (O’Brien), and unanimously approved to hire Oliveri to print 50 sets.

 

SES--- Project Schedule was presented and reviewed.  MPN expects list of comments from SFU 1/23/04, which will be returned to them 2 weeks later.   Authorization to bid is expected 2/10/04.  Advertising may follow SHS by a month.

 

MBA---meeting with staff was held.  Discussion of some changes in space use of Central Office; must be finalized by staff soon.  Also some comments about locker rooms and office of P.E. staff to be finalized.  Relocation of CO---Jim Morrow is looking at tech costs, off-campus vs on-campus, then site visitations will start by staff.

 

A proposed Invitation to Bid was distributed.  Attorney’s comments were shared.

 

Motion to approve bill for $2470.00, 12/8/03, Inv. 120421, Review of SHS Bid Document, Gordon, Muir, and Foley, LLP, unanimously approved (O’Brien, Cowles).

 

Motion to adjourn at 8:50pm.

 

Respectfully submitted,

 

 

Joan Formeister, Secretary