SOMERS SCHOOL BUILDING
CONSTRUCTION COMMITTEE
October 28,
2004
Members
Present: T.Cowles, K.Klein, J.O’Brien,
H.Broer, P.Roland, J.Formeister,
J.Butler
Ex-Officio: T.Jefferson
Others: M.Beaulieu, E.Zahner
The meeting
was called to order at 7:33pm by Chairman Roland.
Minutes of
the 9/23/04 meeting (O’Brien, Klein) and 10/14/04 meeting (O’Brien, Klein) were
unanimously approved as presented.
SHS---A
motion was made (O’Brien), seconded (Broer), and unanimously approved to accept
Change Order #2 from All-Phase for $32,195 (expanding Media Center). A motion was made (Cowles), seconded
(Butler), and unanimously approved to accept Change Order #3 from All-Phase for
$4564 (credit for concrete walls, foundation depth).
A motion
was made (Broer), seconded (O’Brien), and unanimously approved for Change Order
#4 from All-Phase for $12,137.
Copies of a
schedule dated 10/15/04 were distributed, followed by much discussion. The Committee asks that a baseline schedule
be provided against new schedules. The
Committee has concerns about the present schedule. The 6/18/04 schedule reflected Completion of Job 3/2/05, and the
10/15/04 schedule states 4/11/05. A motion
was made (Broer), seconded (O’Brien), and unanimously approved to have a
sub-committee of J.Butler, T.Cowles, M.Beaulieu, E.Zahner, and All-Phase reps
discuss the schedule and establish schedule critical path from hereon in.
Discussion
of installation of electrical wiring for C.O. in the new choral room--with no
State approval yet for the C.O. plans, money for this work is not freed
up. The Chairman will speak with the
BOF about securing these funds, to be paid later from C.O. move budget. A motion was made (Butler), seconded
(Cowles), and unanimously approved to approve $1467 for C.O. electrical work
contingent upon MPN producing a change order.
Report from
E.Zahner was distributed.
SES---copies
of a new schedule were distributed.
This job is going along well and ahead of schedule. Report from E.Zahner was reviewed. It was stated that the Building Inspector is
working well with us.
Cafeteria—P.Roland
had a conversation with J.Petronella from Enfield Builders, stating we could do
a cafeteria expansion for no more than $160,000 for Option B. Since we’re in good shape with this project
and the amount of money in contingency, the consensus of the Committee is that
we are able to reinstate an expansion of the cafeteria based on the usefulness
of having the additional space in the future.
A motion was made (O’Brien), seconded (Broer), and unanimously approved
to approve not more than $160,000 for Option B, cafeteria expansion.
A motion
was made (Cowles), seconded (Klein), and unanimously approved for a proposal
for a Change Order to fix floors in Rooms 101, 102, 201 for $5442. A motion was made (O’Brien), seconded
(Cowles), and unanimously approved for a Change Order to equip the temporary
Special Ed office space for an amount not to exceed $6550, to be covered by the
C.O. move budget, contingent upon approval by MPN. This item will also be discussed with the BOF since the C.O.
plans are not yet approved.
MBA---the
State SFU estimates the date of 11/26/04 for plan review completion. Three Code
Modification Requests will be sent to the Chairman. A Phase 1 Environmental Site Assessment report was completed by
TRC.
Bills---the
following bills were all unanimously approved for payment:
All-Phase, 9/30/04, App#6, $211,907.95 (Butler, Klein)
Enfield Builders, 9/30/04, App#4, $254,805.20
(approved pending receipt of all lien
waivers)
(Cowles, Klein)
IMTL, 10/18/04, 6624-E, $960 (approved by E.Zahner)
6546-G, $1595 (approved by E.Zahner) (O’Brien, Broer)
MPN, 10/29/04, Inv.#13855 MBA, $36,949.33
Inv.#13856
CO, $4435.43
9/30/04, Inv.#13817 SES, $2476.41
Inv.#13818
MBA, $36,700.78
Inv.#13816
SHS, $3571.07
Inv.#13819
CO, $4444.76 (O’Brien, Klein)
Emery Zahner, 10/18/04, SHS, $700.00
SES, $1600.00 (Butler,
Klein)
Macchi Engineers LLC, 10/6/04, SHS, $1166.67
SES, $2000.00 (Cowles, Klein)
Brooks Labs, 9/23/04, Inv.#1543, $470.00 (O’Brien, Butler)
Motion to
adjourn at 9:10pm.
Respectfully
submitted,
Joan
Formeister, Secretary