SOMERS SCHOOL BUILDING
CONSTRUCTION COMMITTEE
January 13,
2005
Members
Present: H.Broer, J.Butler, K.Klein,
J.MacFeat, J.Formeister, P.Roland (8:00)
Ex-Officio: B.Boutwell
Others: D.Moser, E.Zahner
The meeting
was called to order at 7:33pm by J.Formeister.
Minutes of
the 12/16/04 meeting were unanimously approved as presented (Klein, Broer).
SHS---E.Zahner
distributed and reviewed his written report and stated there are no real issues
with SHS project.
D.Moser
distributed Critical Path Schedule; J.Butler stated he did not receive this via
e-mail as requested last month, though A.Seagrave had told E.Zahner it was
sent. Discussion of completion date of
4/12/05 followed; Committee wants to be sure more days do not turn into more
money, yet does not want project rushed.
Building Inspector is in 3 times weekly. E.Zahner stated G.Lloyd said he’ll be more certain of completion
date in a couple of weeks. Question of
Builder’s risk insurance and cost to us.
D.Moser
stated he received on 1/13/05 verbal and faxed approval on FF&E from
State. We can now go out to bid and
also order remainder of items.
B.Boutwell will handle ordering.
Discussion
of air conditioning in temporary C.O. space---need 4 units, estimate very high,
are stand-alone units possible?
E.Zahner will discuss with Greg Genlot for ideas.
SES---E.Zahner’s
written report was reviewed, 5 items to be addressed. We can take a credit for mixing valve in janitor’s closet, not
needed with electric water heater (for classrooms and bathrooms). Condensation pump in band/choral areas not
needed. Brick wall with
lockers---E.Zahner suggested sheet rock over brick, which is
deteriorating. Efis wall---on one area,
existing brick should be efis. Shut-off
valve needed, no way to isolate plumbing of new wing. A motion was made (Butler), seconded (MacFeat), and unanimously
approved to give the Chairman permission to work out pricing details with
E.Zahner to go ahead with these 5 items.
Eventually there will be change orders for them. Schedule---will finish cafeteria addition
3/17/05.
MBA---D.Moser
reported that 6 contractors attended mandatory pre-bid walk-through. All asked for an extension to write
bids. Prices of various materials are
going up. A motion was made (Klein),
seconded (Butler), and unanimously approved to open bids on 2/2/05 at 2pm
instead of 1/19/05.
A Special
Inspection Proposal was received from Macchi Eng. for $6000. This firm has worked well with us on present
projects. Motion to approve Macchi
Eng.’s proposal for MBA for $6000 was unanimously approved (MacFeat, Broer).
Chart with
prices from testing companies was reviewed.
Motion to approve Special Testing as MBA testing service was unanimously
approved (Butler, Broer).
Correspondence---P.Roland
noted a letter he had written to the BOE regarding B.Boutwell’s diligent and
invaluable service to the Building Committee.
The
following bills were unanimously approved by the Committee:
Moser Pilon
Nelson $2463,85, 12/20/04
Inv.#13950, SES
$3218.83, 12/30/04 Inv.#13951, MBA
$3576.19, 12/30/04 Inv.#13949, SHS
$388.80, 12/30/04 Inv.#13917, CO (MacFeat, Klein)
Town of
Somers $318.75, 12/13/04, 12/14/04, 12/22/04, Fire
Watch (Butler, Klein)
SBC $103.59,
12/9/04, C of W phone (Broer, MacFeat)
Emery
Zahner $700.00, 1/10/05
Inv.#758608, SHS
$1600.00, 1/10/05
Inv.#758609, SES (Klein, Butler)
All-Phase
Enterprises $239,063.27, 12/30/04
App#9 (Klein, Broer)
Enfield
Builders $172,518.2, 1/12/05
App.#6 (Butler, Broer)
Motion to
adjourn at 9:12pm.
Respectfully
submitted,
Joan
Formeister, Secretary