SOMERS SCHOOL BUILDING CONSTRUCTION
COMMITTEE
July 21,
2005
Members
Present: P.Roland, K.Klein, H.Broer,
J.MacFeat, T.Cowles, J.O’Brien,
J.Formeister
Others: Paul Marean (Garden Design Associates),
Terri Henderson (BOE Chair), E,Zahner
(7:45), D.Moser (7:45), Bill
Meier (Fire Chief, 8:00), W.Summers (8:00)
The meeting
was called to order at 7:33pm by Chairman Roland.
SHS---courtyard
discussion with design plan presented for Frank’s Landscape Construction by
P.Marean. Question if maintenance-free,
mulch until plants spread, watering after planting, J.MacFeat stated plan
should work. Motion unanimously
approved to approve plan as presented, with one change, add short walkway and
area for benches (benches not included), with expenditure up to $7000 (O’Brien,
MacFeat). K.Klein and J.MacFeat will
look into possibility of tech classes building benches.
Building
Inspector has signed off on everything.
We’re still holding last payment.
Motion unanimously approved to pay $68,212.79 upon delivery of disc of
as-built drawings (O’Brien, Cowles).
Change
Order for $4396.80 was approved at June meeting but not paid.
J.MacFeat
expressed concern about Johnson controls, training is planned. Enunciator
panel—J,MacFeat has quote for $1100. Motion unanimously approved to expend
$1100 for improvements to enunciator panel as approved by W.Summers (Cowles,
Broer).
Valued
engineered items as discussed at June meeting, cabinets, cabinet doors, etc.—Motion
to pay $24,874.30 to All-Phase for listed items unanimously approved (Cowles,
Broer).
Motion to
amend agenda to discussion of MBA unanimously approved (Cowles, Broer).
Fire
alarms--Dust is causing alarms to go off.
By 8/1/05 asbestos abatement should be complete. Bill Meier stated they have to stop going
off; the covering is not working; there have been 8 alarms in 3 weeks. Since 7/16/05 the Fire Dept. has been using
non-emergency single officer response. B.Boutwell
received a letter from the insurance agent stating the alarms cannot be turned
off. When next year’s asbestos
abatement begins, the Fire Dept. will be notified. It is the responsibility of the contractor to maintain systems
that are in place. The Committee agreed
that the one-man response is an acceptable solution.
Schedule—copies
of schedule dated 7/13/05 were distributed.
Slight
change to exit from bus loop is necessary to accommodate buses turning onto
Vision Blvd.
Motion
unanimously approved to spend up to $3100.00 to remove 3 trees and widen bus
loop exit
(O’Brien,
MacFeat).
Discussion
about resurfacing front parking lot, which will not look good when all else is
new.
Motion
unanimously approved to authorize Chairman to approve contract for up to
$13,500 to pave front lot and do curbs (O’Brien, Cowles).
FF&E—Total
in budget is $698,000; package now is $594,000, with $261,000 in furniture
items and $333,000 technology. MBA
staff needs to do final review, Building Committee and BOE must approve by
9/15/05, then to state SFU. Instead of
placing separate orders or storing items, it was the consensus that all
furniture should be ordered toward completion date of project, with tech
purchases being made as needed for renovated classrooms. MPN reported that
wiring for telephone/video should be separated out from FF&E and EBI
requested to bid. The MBA trunk of the
phone/data system has 100 lines max available; currently 87 are used; there is
a problem in one of the trunk splices between MBA and SHS which needs to be
repaired prior to opening of new classroom space 12/05. J.MacFeat will work with BOE and B.Boutwell
to resolve by Committee’s September meeting.
E.Zahner
reported double ceilings were found in shop room. Also the ceiling in the lower corridor by cafeteria cannot be
raised as much as hoped, since there are water and electric pipes. Instead of 8 feet it can probably be raised
to 7’9”.
W. Summers
stated he wants the propane tank in the back of MBA fenced. He expressed concern about where the gas
line from the tank goes.
SES---E.Zahner
stated he hopes tile work in the front of the cafeteria will be finished by the
end of the month, then masonry will be completed. SES will be done by the start of school. Motion unanimously approved for Change Order
#9 for $6554.00 to EBI, winter conditions $4791.00 and added flashing at
cafeteria roof $1763.00 (Klein, Cowles).
The
following bills were unanimously approved by the Committee:
Emery
Zahner, 6/24/05, Inv.#758639 thru #758641, $2300.00
7/10/05 &
7/11/05, Inv.#758643 thru #758646, $2300.00 (Broer, Klein)
MPN,
6/30/05, Inv.#14187 (MBA), $4409.66
Inv.#14188 (CO), $517.88 (Broer, Cowles)
Enfield
Builders, 6/30/05, App#3 (MBA), $238,539.15
App#3
(CO), $178,261.00
App#12 (SES), $11,779.05
(O’Brien, Broer)
SBC,
6/9/05, SHS $49.55
SES, $49.55
Flinn
Scientific, 7/1/05, Inv.#922827 (SHS), $3629.71
7/6/05, Inv.#923354
(SHS), $11,429.81
Insalco
Corp., 6/7/05, Inv.#42505 (SHS), $469.00 (all 7 vendors
listed, Klein, Cowles)
7/1/05, Inv.#42629
(SHS), $5270.64
Macchi
Eng., SomersAvery3, 7/1/05, $1000.00
Robert
Lord, 6/29/05, Inv.#23304A, $5575.36
Somers
Public Schools, 6/10/05 (boxes, MBA/CO), $875.00
AFS&V,
6/28/05, Inv.#8172-2 (MBA/CO), $7680.00
Motion to
adjourn at 9:32pm.
Respectfully
submitted,
Joan
Formeister, Secretary