SOMERS SCHOOL BUILDING CONSTRUCTION COMMITTEE
November 10, 2005
Members
Present: T.Cowles, H.Broer, J.MacFeat,
J.Formeister, K.Klein, J.Butler
Ex-Officio: B.Boutwell
Others: H.Pearson, N.Barry, W.Summers., B.Meier
The meeting
was called to order at 7:35pm by J.Formeister.
Minutes of
the 10/13/05 meeting were unanimously approved as presented (MacFeat, Broer).
SHS---outstanding
issues remain enunciator panel, sprinkler signage.
SES---outside
tile is installed. Seeding not
complete. It was noted there were leaks
in the cafeteria but they are not from the construction. There were also leaks at new threshold from
courtyard due to negative pressure in the building, ? need for overhang? Some warranty items are outstanding.
A motion
was unanimously approved, pending B.Boutwell’s verification that it has not
been paid, for Change Order#10 to EBI, conduit wiring for unit heater in
sprinkler room ($607, PCO#28) and adding vinyl base in existing cafeteria
($794, PCO#29). (Butler, Broer)
MBA/CO---W.
Summers and B.Meier spoke to the Committee, requesting we reconsider and remove
abandoned gas pipes. No decision has
yet been made; we have an estimate of $2730 to remove but no estimate for
stickers and labor to label pipes if not removed. The Committee needs the estimate and a deadline for when this has
to be done. Tabled till next meeting.
Outside
lights are all up. Question as to
whether contrast bricks on addition are all the same color, B.Boutwell to check
in daylight. Still waiting for
remaining windows. The addition is
sheetrocked.
N.Barry
stated the wrong carpets were delivered for corridors.
Discussion
of color for entryway roofs; consensus “colonial red” (dark red) first choice,
red second; N.Barry to decide after checking color against brick.
21-day
schedule presented, still no critical path so not too helpful to Committee.
Heat has
been turned on and filters changed. No
complaints. Plan is to change filters
once a month, no cost yet, J.MacFeat will follow up. A staff member called in the Dept. of Public Health and the CEA
(teachers’ union), who did a walk-through---stated it was the cleanest renovate
as new project they had seen. J.MacFeat
also brought out Mark Granville, the asbestos person, because of concern about
some loose floor tiles in cafeteria. No
written reports yet. E.Zahner will be
reminded to have TRC perform air quality tests as previously discussed by
Committee.
Discussion
of plan to move teachers into addition and abatement schedule. Art and Life Skills areas to be renovated
along with 6th grade wing.
This process will take from Jan.-April; there are 9 new temporary
classrooms and one room for teachers/team room. Move will begin over Christmas break. Not enough lockers. Plans
for coat hooks and students keeping backpacks with them.
Cabling
issue---written proposal presented by H.Pearson for resolving cable
issues. Explanation and discussion
followed. Total addition of $96,102 includes
voice, data, video cabling, and tech system throughout the building (5E cable),
eliminates $23,999 from original plan (electrical feeder lines not needed),
adds $5512 for wireless cabling throughout the school, 18 wireless
locations. Change Order #5 to EBI for
$96,102 as listed above was unanimously approved (Butler, Cowles).
FF&E---further
discussion of the FF&E budget followed.
The tech part has been examined by superintendent and others; questioned
if the furniture portion has been examined, as we’re over budget on FF&E
and we originally expected we would have money left over. Details of furniture
can be changed when ordering is done.
B.Boutwell distributed expenses to date, with present estimate of
$537,444 contingency balance.
This
FF&E budget has to be approved again before sending it to the State, since
it has changed since voted on at the 9/15/05 meeting. A motion was made (Cowles), seconded (Klein), and unanimously
approved that the Somers School Building Committee approves the design plans
and project manual for Phase Two of Two of the MBA School, Project #129-0033
EA/RNV and Central Office, Project #129-0035 BE/EA Furnishings, Fixtures, and
Equipment for $682, 923 (including $31,450 for projectors), for submission to
the State Dept. of Ed. and authorizes the Committee Chair to sign the Form
ED042, Request for Review of Plans.
A motion
was made and unanimously approved for Change Order #6 to EBI for $7661.50,
delete mow strip, relocate sprinkler piping, delete demolition of locker room
wall, waterproofing, duct heaters, additional framing bus canopy, plywood for
P.E. office (Butler, Broer).
Meeting
schedule as attached was unanimously approved, second and fourth Thursdays of
each month, with exceptions during holiday periods (Klein, Broer).
The
following bills were unanimously approved:
Emery
Zahner, SES 10/31/05, Inv.#503930, $100.00
MBA 10/31/05,
Inv.#503931, $1100.00
CO 10/31/05,
Inv.#503929, $1100.00 (Klein,
Cowles)
MPN, SES
10/28/05, Inv.#14336, $1478.90
MBA 10/28/05, Inv.#14337, $4378.01
CO 10/28/05, Inv.#14338,
$502.33 (Klein, Cowles)
Misc.
invoices per 11/14/05 memo from B.Boutwell, page 1, except Poland Spring
(Cowles, Klein, one abstention-J.MacFeat)
EBI, SES
10/31/05, App. #14, $49,111.29 (balance $5000 in reserve) (Butler, Cowles)
MBA/CO 10/31/05, App.#7,
$392,094.45 (Broer, Cowles)
Motion to
adjourn at 10:00pm.
Respectfully
submitted,
Joan Formeister,
Secretary