SOMERS SCHOOL BUILDING CONSTRUCTION
COMMITTEE
January 12, 2006
Members
Present: H.Broer, P.Roland, J.Persano,
K.Klein, T.Cowles, J.Butler,
J.Formeister,
J.O’Brien
Ex-Officio: B.Boutwell
Others: N.Barry, E.Zahner, H.Pearson, Pete Lucchini,
Sr., Dave Lucchini, Ed
Flynn, Walt Summers
The meeting
was called to order at 7:32pm by Chairman Roland.
Minutes of
the 12/8/05 meeting were unanimously approved as presented (Klein, Butler).
MBA/CO---students
successfully moved into the new addition 1/9/06. N.Barry thanked E.Zahner and Tucker Foley from EBI for making the
move go smoothly. Teachers are very
happy in the addition.
The dust
issue at MBA has decreased with cold weather.
Additional carpets for 6th grade wing were not delivered as
ordered or on time, so they were sent back and are no longer needed.
New bleachers
are in the gym.
EBI is
working in the 6th grade wing; it’s boarded up now.
H.Pearson
from MPN explained the issue that led to the Fire Watch in place since the
move. Part of the code is not clear and
was interpreted differently by MPN and engineers than by the Town and Fire
Marshall, who believes smoke dampers are needed in ducts above ceilings in
addition. A modification approved by
W.Summers is at the State; we will need 17 additional smoke detectors for
$7000; hopefully early next week we will get the okay and EBI can install 6
detectors needed immediately. The Fire
Watch is costing us $240/day---discussion about whether this is an oversight
and should the Building Committee be responsible for the $7000 plus the Fire
Watch. A motion to acquire 6 smoke
detectors was unanimously approved (O’Brien, Klein). A motion to continue the Fire Watch till the issue is resolved
was unanimously approved (Persano, Butler).
The SFU has
approved our FF&E package, so it’s ready to go out for bid, furniture and
technology separately. When we
advertise furniture, there will be 2 ways to bid, one for 7/07 delivery and one
broken into phases so furniture comes in as areas of the school are completed.
Discussion
of HVAC location in cafeteria. E.Zahner
states it is okay as is.
Discussion
about refurbishing gym divider instead of replacing---will it be
reimbursable? Argument is yes, since it
will be renovated as new and will be written as such.
Two doors to
P.E. teacher’s bathroom are out.
Lights in
gym---presently are on dimmer switches, but 16 new fixtures will not be and
dimmers are desired. One option is to
keep old lights and just add 8 new ones to increase lighting. MPN will look to maintain capacity of
dimming lights.
Various
PCO’s were presented by H.Pearson for sheet metal design, work on bathroom
ceilings, sound walls, elevator shaft work, new markerboards, flange kits,
wiring modification. A motion was
unanimously approved to pay $17,519.50 for Change Order # 7 (O’Brien, Persano).
Old
business----item from last month concerning E.Zahner’s wages. Memo from B.Boutwell shared; budgeted amount
will pay through June, 2007.
A motion was unanimously approved for Change
Order # 15, credit for $400.00 from All-Phase Enterprises, for not installing
cabinetry at SHS (Persano, O’Brien).
The
following bills were unanimously approved by the Committee:
MPN, MBA,
12/30/05, Inv.#14401, $4310.15
CO, 12/30/05, Inv.#14402,
$517.88 (Persano, O’Brien)
E.Zahner,
SES, 12/12/05, Inv.#503944, $100.00
MBA, 12/12/05, Inv.#503945,
$700.00, 12/27/05, Inv.#503947, $1500.00,
1/9/06,
Inv.#150403, $1600.00
CO, 12/12/05, Inv.#503946,
$1500.00, 12/27/05, Inv.#503948, $800.00,
1/9/06,
Inv.#150404, $700.00 (Persano,
Cowles)
EBI,
App.#9, 12/31/05, MBA/CO, $628,501.46
(O’Brien, Persano)
Materials
Testing Inc., MBA, 10/17/05 & 11/21/05, $829.00 (O’Brien, Persano)
Misc. invoices
per 1/13/06 memo from B.Boutwell
(Cowles, Persano)
B.Boutwell
stated he and Ed Sullivan are trying to work out billing process for MBA and CO
components with EBI and H.Pearson.
Motion to
adjourn at 8:55pm.
Respectfully
submitted,
Joan
Formeister, Secretary