SOMERS SCHOOL BUILDING CONSTRUCTION COMMITTEE
February 16, 2006
Members Present: P.Roland, H.Broer, T.Cowles, J.Butler,
J.Formeister, K.Klein
Ex-Officio: B.Boutwell
Others: E.Zahner, M.Beaulieu
The meeting was called to
order at 7:02pm by Chairman Roland.
MBA/CO---contingency now is
$386,161, 90% committed, 53% of the way into total project to date.
HVAC unit on roof—needs
steel reinforcement; E.Zahner needs to move ahead on columns. Price of $19,461 has been suggested, working
to get this figure lower. A motion was
unanimously approved for the necessary expenditure for steel reinforcement
while MPN works with Macchi Eng. on a price (Klein, Butler).
Science room storage
cabinets---this was a deduct to meet the original budget. Will be considered at next meeting when we
have a firm figure.
Interior partition
walls---cannot be sheetrocked, Building Inspector said wood has to come
out. A motion was unanimously approved
for $6666 per wall for 3 walls to be cement (Broer, Cowles).
Band room---consensus of
Committee to leave it as in the plans for now.
Old Business---
Gym dimmers---cost will be
additional $3300. 16 lights are going in, 12 will be returned and exchanged for
lights with dimmers. A motion was
unanimously approved for $3300 additional for lights with dimmers and to bring
wiring up to code (Cowles, Broer).
FF&E---furniture is out
to bid, bids due 2/21/06.
Tech—M.Beaulieu presented final plans.
Will be forwarded to Jim Morrow for a final look.
P.Roland suggested that the
Committee again request the BOE to consider a merit bonus for B.Boutwell as we
did last year, citing his time, effort, and commitment to the Building Project
which is so much appreciated by the Committee.
A motion was unanimously approved for the Chairman to write a letter to
the BOE regarding a bonus for B.Boutwell (Cowles, Butler).
SHS---P.Roland reported
there was some damage to the Field Rd. soccer field nearest SHS; an ATV
accessed it from SHS parking lot. Will
look into putting up a barrier with money still in SHS project.
The following bills were
unanimously approved by the Committee:
Change Order #8, EBI,
2/9/06, deduct $324 for misc. construction changes
(Butler, Klein)
E.Zahner, MBA, 1/23/06,
Inv.#150405 $2000.00; 2/6/06,
Inv.#150407 $2300.00
CO, 1/23/06, Inv.#150406 $300.00
(Cowles, Broer)
MPN, MBA, 1/31/06, Inv.#14448 $4279.88
CO,
1/31/06, Inv.#14447 $517.88 (Klein, Cowles)
EBI, MBA App.#10, 1/31/06 $284,529.05
(Klein, Broer)
Misc. invoices per 2/17/06
memo from B.Boutwell (Cowles,
Klein)
Materials Testing, 2/8/06, Inv.#8205-IS, $555.00 (Cowles, Klein)
TRC, 2/13/06,
$812.00 (asbestos testing)
(Klein, Butler)
Motion to adjourn at 7:52pm.
Respectfully submitted,
Joan Formeister, Secretary