SOMERS SCHOOL BUILDING CONSTRUCTION COMMITTEE
May 11, 2006
Members Present: J.Persano, H.Broer, K.Klein, T.Cowles,
J.Formeister,
J.MacFeat, J.O’Brien
Ex-Officio: B.Boutwell
Others: H.Pearson, E.Zahner, E.Flynn (LMG),
W.Summers
The meeting was called to
order at 7:30pm by Vice-Chair J.Persano.
Minutes of the 3/9/06
meeting were unanimously approved as presented.
MBA---6th grade
wing is complete, short punch list. Art
Room complete. 7th and 8th
grade wings—floors going in, ceilings in, ahead of schedule. P.E. office and girls’ locker room demo’ed
now. Landscaper coming next week. Site contractors are in cleaning up.
End of June front rooms
(offices) will be demo’ed.
Contracts for FF&E have
been sent out. Have to coordinate
deliveries, B.Boutwell and E.Zahner are discussing this.
Need new kiln, old one
from1976. Quote for about $2500.
Some new clocks and
additional speakers are needed per E.Zahner.
H.Pearson provided info on
the following PCO’s:
#39--small electrical items
when ceilings removed, $5092.
#40—upper cabinets science
rooms, on hold from March, E.Zahner states we might not need so many, $38,005.
#45—relocation of diffusers
in 9 classrooms done, 11 more to go, and corridor grills that had to be
changed, total $7405
#46—6th grade
science room, unit heater in ceiling, $1923 to remove and trash unit.
#47—Art Room, new duct work
$11,642 (this room and science room not as indicated in drawings).
#48—electrical work $3212.
#49—existing masonry wall,
$598 to create sound barrier between 2 classrooms.
#50—added millwork, credit
of $2300 on hold.
#51—registers, grills,
diffusers in Art Room, change ductwork $2435.
#52—data closet, add exhaust
fan $1086.
#53—kiln room, modifications
to exhaust fan $1580.
#54—generator, size has
changed, new one will not fit in present room, $10,780 to put it outside and
protect it. A motion was made by
J.O’Brien, seconded by T.Cowles to approve $10,780 for adaptations for new
generator, passed (2 opposed, J.MacFeat, J.Formeister).
A motion was unanimously
approved to accept PCO’s for items already completed, 45,46,47,48,49,51
(O’Brien, Cowles).
E.Flynn explained redesign
of one grease trap in cafeteria instead of 3 as required by DEP. Below floor, automatic pump, $30,000. DEP will require this to be monitored. A motion was unanimously approved to go
ahead with the redesign for about $30,000 as proposed by E.Flynn (O’Brien,
Cowles).
Discussion about added
expenses of numerous and continual PCO’s.
B.Boutwell reported there is contingency left in the $160,000’s out of
original $436,000. Project is 61.4%
completed. Work in the offices,
cafeteria, and other areas has not yet begun.
Security work and
updates—Sonitrol proposal for $28,450.
B.Boutwell will find out if this can be covered in building
project. A motion was unanimously
approved for $28,450 for security work contingent upon B.Boutwell’s checkjng
that it’s part of renovation and EBI can do the work (O’Brien, Cowles).
The following bills were
unanimously approved by the Committee:
Misc. vendors per memo from
B.Boutwell 5/12/06 (Broer, O’Brien)
MPN—MBA 3/24/06, Inv.#14512,
$4286.96; 4/30/06, Inv.#14550, $4293.84
CO, 3/24/06, Inv.#14513, $517.88; 4/30/06, Inv.#14551,
$517.89
(O’Brien, Cowles)
EBI---App.#12 MBA, 3/31/06,
$248,003.60, already paid
App.#13 MBA, 4/30/06, $303,380.65, pending E.Zahner
checking equipment stored in warehouse, title insurance, and bonding (O’Brien, Broer)
E.Zahner---total $9200.00,
MBA, for inv.#150411, 150415, 150416, 150457 dated 3/20/06, 4/5/06, 4/19/06,
5/2/06 (Broer, Cowles)
Motion to adjourn at 8:55pm.
Respectfully submitted,
Joan Formeister, Secretary