SOMERS SCHOOL BUILDING
CONSTRUCTION COMMITTEE
January 11, 2007
Members Present: J.MacFeat, J.O'Brien, H.Broer, J.Formeister,
P.Roland
Ex-Officio: B.Boutwell
Others: H.Pearson, N.Barry
The meeting was called to
order at 7:33pm by Chairman Roland.
Minutes of the 12/14/06
meeting were unanimously approved as presented
(Broer, Formeister).
MBA---H.Pearson reported
Phase 5 demolition is almost complete.
Need for
some simplification of work
in ceilings of Media Center/AV Room, might be
savings.
Asbestos abatement of
science rooms will be over upcoming long holiday
weekend.
Phase 6 FF&E coming
1/16. Janis Newell of JNI Design will
be present to
oversee deliveries. Building Inspector has been active,
especially
concerning air return/flow
in administrative area.
Media Center area--EBI
believes Media Center may be ready for FF&E as early
as April1. Cabinets in AV storage with orange
laminate--looking at
disposing of them and
putting in dividers beneath countertops.
Door to
outside--EBI can
salvage/maintain existing door; there will be an
electricity expense, exit
signs and lights. Committee and N.Barry
want the
door kept. Waiting for cost figure.
Kitchen issues have been
resolved, with completion the first of February.
Cafeteria is being used now
for cold lunches.
Budget sheet was distributed
by H.Pearson. As of 12/30/07, project
was
87.5% complete with 91.32%
contingency spent after this meeting.
Discussion was followed by a
motion to approve PCO's 93 and 94 for $2667.00,
unanimously approved (Broer,
O'Brien).
There are several pending
issues.
H.Pearson distributed a
communications sheet with phone numbers of key
people.
P.Roland discussed need for
a replacement to do some of Emery Zahner's job.
He will call Harold Pease,
who has experience in this area, about part-time
work. MPN has offered additional services,
increased site observation and
coordination, every other
week alternating with weeks of site meetings;
half-day once every two
weeks will cost Committee $800-$1000.
Janis Newell
will charge $75/hour to be
on site for FF&E.
The First Selectman and Town
Attorney were contacted with questions of
legality of paying
E.Zahner. Response to date is "not
sure". He has been
paid through December. A motion was made and unanimously approved
to
continue to pay E.Zahner his
salary and FF&E stipend (MacFeat, O'Brien). A
motion was made and approved
to pay J.Newell for FF&E fees as needed and to
pay MPN per 1/5/07 memo till
Committee's February meeting, 4 in favor,
Formeister opposed (O'Brien,
MacFeat).
P.Roland recommended that
Committee members do walk-throughs of MBA/CO and
make notes of items for
corrections and punch lists.
N.Barry commented that there
are no speakers or clocks in the gym, no
switches to turn off lights,
motion sensors not working, weather stripping
needed on doors.
P.Roland and B.Boutwell
attended the December BOF meeting. SES
and SHS
contingency money has been
set aside, and the BOF approved $34,000 for gym
floor refinishing and
bleachers. The BOS has transferred all
but the
$34,000.
Brief discussion of plaques,
with paper sample distributed by H.Pearson.
P.Roland and the Committee
thank J.MacFeat and crew, N.Barry and staff, MPN
that all went well with the
move during Christmas break.
The following bills were
unanimously approved by the Committee:
EBI, App.#21, 12/31/06, MBA $405,466.55 (Broer, MacFeat)
Emery Zahner, MBA, 12/11,
12/18, 12/25 $3450.00
FF&E, 12/11, 12/18, 12/25 $600.00 (Broer,
O'Brien)
MPN, Inv.#14881, 12/31/06, MBA $4284.85
Inv.#14882, 12/31/06, CO
$517.88 (Broer, O'Brien)
Misc.vendors per 1/11/07
memo from B.Boutwell, with payment to Equipment
Environments, Inc. for
$22,496.70, Inv.#15898 held till all is delivered.
(O'Brien, MacFeat)
Motion to adjourn at 8:55pm.
Respectfully submitted,
Joan Formeister, Secretary