SOMERS SCHOOL BUILDING CONSTRUCTION COMMITTEE
October 11, 2007
Members Present: T.Cowles, J.MacFeat, J.Formeister,
J.O’Brien, J.Persano
Others: H.Pearson, H.Pease
The meeting was called to
order at 7:55pm by J.Persano.
Minutes of the 9/13/07 meeting
were unanimously approved as presented with one change: top of page 2,
“independent purchase order” instead of “Change Order#” (O’Brien, Cowles).
MBA/CO---no update from
Labor Dept. regarding prevailing wage issue.
H.Pearson distributed a memo
with project close out update.
J.MacFeat stated still
working on HVAC before we can sign off.
Issue of covers for roof
mounted HVAC units raised last month—the manufacturer does not make covers, the
units are complete.
H.Pease reported there are
still items Robert Lord has not sent us and B.Boutwell is holding $30,000 for
them. Screens are due this week. Assisted listening in gym is working
well. Speed of wrapping up punch list
has been excellent.
Committee is still retaining
$100,000; all documents need to be furnished, small punch list outstanding,
B&G issue to be resolved.
H.Pearson stated MPN does
not plan to attend any more Building Committee meetings but will follow through
with project closeout via phone and e-mail.
The following bills were
unanimously approved by the Committee:
Harold Pease, Inv.#
9/14/2007, MBA, $575.00
Inv.# 9/28/2007, MBA, $312.50 (O’Brien, Cowles)
Misc. vendors per B.Boutwell
memo dated 10/11/07 (Cowles,
O’Brien)
Committee members will be
notified of next meeting date.
Motion to adjourn at 8:12pm.
Respectfully submitted,
Joan Formeister, Secretary